PMP考试用到的公式Budgeted Cost of Work Scheduled = BCWS = Planned Value = PVBudgeted Cost of Work Performed = BCWP = Earned Value = EVActual Cost of Work Performed = ACWP = Actual Cost = ACBudget at Completion = BACEstimate at Completion = EACEstimate to Complete = ETCVariance at Completion = VACVariance = Plan - ActualCost Variance CV = BCWP - ACWP = EV - ACSchedule Variance SV = BCWP - BCWS = EV - PVCost Performance Index CPI = BCWP / ACWP = EV / ACSchedule Performance Index SPI = BCWP / BCWS = EV / PVEstimate at Completion EAC = BAC / CPIEstimate to Completion ETC = EAC - ACWPVariance at Completion VAC = BAC - EACQ U A L I T Y - CoQ = ( ( Review Efforts + Test Efforts + Training Efforts + Rework Efforts + Efforts of Prevention) / Total Efforts) x 100 % PERT = O + 4ML + P - 6 MEAN - Average MODE - The “most found” number RANGE - Largest - Smallest Measure. MEDIUM - No in the middle or avg. of 2 middle Nos STD. DEV. OF TASK = P - O _ 6 TASK VAR. = (P O) 2 = Std. Dev 2 _ 6 _ CP STD. DEV. = + + SIGMA 1 = 68.26 2 = 95.46 3 = 99.73 6 = 99.99 Channels of Communication - COMM = (N2 - N) / 2 = (N x (N 1) / 2 P R O J E C T S E L E C T I O N - PV = F V . - (1+r) FV = PV x (1+r) NPV = S ( PV + PV + PV + PV ) - - - - (1+r) (1+r) (1+r) (1+r) Cash Flow = Cash Inflow Cash Outflow Discounted Cash Flow = CF x Discount Factor ARR = S Cash Flow / No. of Years ROI = (ARR / Investment) * 100 % BCR = Benefits / Cost Exp. Value = Probability % x Consequence $ Class of Estimates - Definitive +5% Capital Cost +10-15% Appropriation +15-25% Feasibility +25-35% Order of Magnitude +35% Contract Incentives - Savings = Target Cost Actual Cost Bonus = Savings x Percentage Contract Cost = Bonus + Fees Total Cost = Actual Cost + Contract Cost E A R N E D V A L U E A N A L Y S I S - PV (Present Value) = BCWS (Budgeted Cost of Work Schedule) EV (Earned Value) = BCWP (Budgeted Cost of Work Performed) AC (Actual Cost) = ACWP (Actual Cost of Work Performed) CV = EV AC CPI = EV / AC (efficiency) SV = EV PV SPI = EV / PV ETC = BAC EV or (BAC EV) / CPI EAC = AC + ETC EAC = BAC / CPI VAC = BAC EAC % COMPLETE = EV / BAC x 100 % SPENT = AC / BAC x 100 CV% = CV / EV x 100 SV% = SV / PV x 100 EASY REFERENCE TO PROJECT MANAGEMENT COST EQUATIONSTheProjects Budget:PV:Planned Value (PreviouslyCalled BCWS:Budgeted Cost of WorkScheduled)Theplanned value is the project budgetthat is part portion of the approvedcost estimate that is planned to be spenton the activity during a givenperiod.TheProjects Actual Cost:AC:Actual Cost (PreviouslyCalled ACWP:Actual Cost of WorkPerformed)The actual cost that is thetotal of direct and indirect costs incurred in accomplishing work on theactivity during the given period.TheProjects Earned Value:EV:Earned Value (Previouslyand Interchangeably Called BCWP:Budgeted Cost of Work Performed)EV is the method for measuring projectperformance.Itcomparesthe amount of work planned with what was actually accomplishedtodetermine if cost and schedule performance is as planned.Theearned value, previously and interchangeably called the Budgeted Cost ofWork Performed (BCWP), is a percentage of the total budget equal to thework actually performed.CostVariance:CV:Cost VarianceCV is any difference from the estimatedcost of an activity and the actual cost of that activity.In earnedvalue analysis, CV = EV ACScheduleVariance:SV:Schedule VarianceSV is any difference from the between thescheduled completion of an activity and the actual completion of thatactivity.In earnedvalue analysis, SV = EV - PVCostPerformance Index:CPI:Cost Performance IndexCPI is the ratio of budget cost to actualcosts.In earned value analysis, CPI =(EV/AC)CumulativeCPI = (sum of all individual EV budgets / sum of all individual ACs)SchedulePerformance Index:SPI:Schedule Performance IndexThe SPI is used in some application areasto forecast the project completion date.SPI = (EV/PV)(Sourcefor above equations:PMBOK, Section 10.3.2.4, Publishedby the Project Management Institute (PMI), 2000 edition)Valuable Hints NOT Written in Project Management BooksAbout Costs (Ormore succinctly “How to know youre in trouble”)When EVis used in a cost variance equation, it always goes first:CV = EV AC(ValuableHint:If you get a negative number, yourproject is over budget.)When EVis used in a schedule variance equation, it always goes first.SV = EV - PV(ValuableHint:If you get a negative number, yourproject will overrun its schedule.)
展开阅读全文
相关资源
相关搜索

当前位置:首页 > 图纸专区 > 考试试卷


copyright@ 2023-2025  zhuangpeitu.com 装配图网版权所有   联系电话:18123376007

备案号:ICP2024067431-1 川公网安备51140202000466号


本站为文档C2C交易模式,即用户上传的文档直接被用户下载,本站只是中间服务平台,本站所有文档下载所得的收益归上传人(含作者)所有。装配图网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对上载内容本身不做任何修改或编辑。若文档所含内容侵犯了您的版权或隐私,请立即通知装配图网,我们立即给予删除!